Monday, February 14, 2011

Drywall


Drywalling the Family Room







The Family Room ceiling is wood - it will get done at the same time as wood floors...
...hopefully next week...

View from Family Room to Kitchen


Master Bathroom tub is in...
it had to get installed prior to tile next week...






The Girls room is almost done - if all goes well they can move back in next week after the drywall is mud and taped...


Wednesday, February 9, 2011

Paper and Insulation

After passing the rough framing inspection we began waterproofing the house by wrapping it in two layers of water protective paper.  When that was done we also insulated the inside of the house with a "green product" registered by the National Green Building Council....










We had the house professionally insulated - they foam every crack and crevice, between windows and studs and plywood to keep air infiltration from seeping in or out....